Permit Application Information

Electrical

Electrical Permits are required for any installation, modification, or repair, of electrical systems including:

  • Concealed Wiring
  • Electrical Service 

Electrical Permits are not required for:

If a permit is required, this guide may help you though the permit process.

 

An Electrical Permit Package consists of:

  • One Electrical Permit Application
  • Three drawings of the installation, modification, or repair
  • Two copies of electrical calculations if required 

Preparing the documents

  1. Print off or pick up an Electrical Permit Application.  Fill out all information and sign application as contractor or owner / builder.
  2. When plans are drawn by:
    1. Architect or Engineer – Plans must be wet stamped and signed on every page.
    2. Contractor – Plans must list contractor information and be signed on every applicable page.
    3. Owner – Plans must be designed and signed by owner of every page.  An owner can only draw plans for his own place of residence.

Submitting the Application

  1. Bring the Electrical Permit Package to the Mesquite Building Department, located in City Hall at 10 E. Mesquite Blvd.
  2. A submittal fee must be paid when application is submitted.  This fee will be applied to the permit. ($40 for Residential and $75 for Commercial)
  3. Plan review time is approximately 10-21 working days each time the application is submitted.  Complete and accurate plans will shorten the time needed for review and resubmittal.

Corrections and Resubmitting

  1. If corrections are needed on the plans, the plan reviewer will call for you to pick up the plans.  Plan Review Comments will be attached to the plans listing the corrections needed.
  2. Make the corrections and resubmit a full Electrical Permit Package, Comment Sheet, and Sign-Off Sheet.  No further payment is needed for resubmittal.

Picking up the Approved Permit

  1. The Permit Technician will call when the permit is approved.  They will tell you if additional fees are required.
  2. Come in to the Mesquite Building Department and pay additional fees, if any.  You will be given a copy of the permit, an approved set of plans, and your receipt.
  3. If you are not sure of what inspections will be required, talk to the Permit Technician before you leave.

What’s the Next Step?

See our handout How to Schedule an Inspection for instructions on scheduling inspections.

Contact Information
Carolyn Harding
10 East Mesquite Blvd.
Mesquite, NV 89027
702-346-2835
charding@mesquitenv.gov
 

City of Mesquite 10 E. Mesquite Blvd., Mesquite, NV 89027 | 702-346-5295 | Contact Us
©2007 City of Mesquite | Privacy, Security, Acceptable Use policies