Permit Application Information

Wall

Wall Permits are required for:

  • Concrete walls over 4 feet high
  • Block walls over 4 feet high
  • Retaining walls over 2 feet high
  • Rockery Walls (see requirements for Rockery Walls)

Wall Permits are not required for fences up to 6 feet in height, including:

  • Wood fences
  • Chain link fences
  • Vinyl or plastic fences
  • Wrought iron fences

If a permit is required, this guide may help you though the permit process.

 

A Wall Permit Package consists of:

  • One Wall Permit Application
  • Two Plot Plans, see example of a Plot Plan
  • Two Wall City Standards (Retaining wall over two feet high and non-retaining walls over 6 feet high must be engineered by a Nevada Licensed Engineer.)
  • One Property Line Authorization (Required for walls built on shared property line)

Preparing the documents

1.       Print off or pick up a Wall Permit Application.  Fill out all information and sign application.  

2.       Print off two of Mesquite’s approved Wall City Standards, or if required, obtain a plan from a Nevada Licensed Engineer.

3.       On minimum 8 ½ x 11 sheet of paper, draw a Plot Plan showing the location of each wall, height of each wall, and any gates installed.

4.       If wall is to be located on a shared property line, a notarized Property Line Authorization must be signed by both property owners for each wall or portion of wall on a shared property line.

Submitting the Application

1.       Bring the Wall Permit Package to the Mesquite Building Department, located in City Hall at 10 E. Mesquite Blvd.

2.       A $40 submittal fee must be paid when application is submitted.  This fee will be applied to the permit.

3.       Plan review time is approximately 10-21 working days each time the application is submitted.  Complete and accurate plans will shorten the time needed for review and resubmittal.

Corrections and Resubmitting

1.       If corrections are needed on the plans, the plan reviewer will call for you to pick up the plans.  Plan Review Comments will be with the plans listing the corrections needed.

2.       Make the corrections and resubmit a full Wall Permit Package, Comment Sheet, and Sign Off Sheet.  No further payment is needed for resubmittal.

Picking up the Approved Permit

1.       The Permit Technician will call when the permit is approved.  They will tell you if additional fees are required.

2.       Come in to the Mesquite Building Department and pay any additional fees.  You will be given a copy of the permit, the Wall Detail, the Plot Plan and your receipt.

3.       If you are not sure of what inspections will be required, talk to the Permit Technician before you leave.

What’s the Next Step?

See our handout How to Schedule an Inspection for instructions on scheduling inspections.

 

 

Contact Information
Carolyn Harding
10 East Mesquite Blvd.
Mesquite, NV 89027
702-346-2835